Loading of all dismantled crane components onto transport vehicles.
Deploy trained banksmen to manage pedestrian traffic and coordinate the entry/exit of flatbed trucks transporting the dismantled crane sections.
Remove the fixing pins from the foundation anchors or floor-climbing collars, lifting the final base mast section away. 6. Comprehensive Risk Assessment and Mitigation Matrix tower crane dismantling method statement
Carefully remove the main connecting pins securing the jib foot to the slewing platform.
Deploy trained watchpersons to prevent unauthorized entry into the drop zone. Loading of all dismantled crane components onto transport
Take the load strain, then remove the remaining counterweight blocks left for balance. Disconnect the counter-jib tie rods.
Specifically Part 2 for inspection, testing, and dismantling (United Kingdom). Take the load strain, then remove the remaining
This document outlines the detailed procedures for the safe dismantling of a at [Insert Project Name/Site Location] . The objective is to disassemble the crane, remove all components, and clear the site safely. 2. Pre-Dismantling Preparations
Crucial: Always leave the mandatory "balance weight" on the counter-jib (usually one block closest to the tower mast) to prevent the crane from tipping forward when the main jib is removed. Step 5.4: Removal of the Main Jib
Hard hats with chin straps, safety boots, high-visibility vests, and safety glasses.